Correct Installation Steps for M16 Connectors

  1. Power Off: Ensure the circuit is completely de-energized before installation to prevent electrical hazards
  2. Align Locating Pin: Match the positioning pin with the slot to ensure correct orientation of the connector
  3. Push to Mate: Gently push the male and female connectors together until fully engaged (do not force)
  4. Hand-Tighten Thread Ring: Screw the threaded ring by hand until noticeable resistance is felt
  5. Torque to Specification: Use a torque wrench to tighten to 60 cNm (rated torque) for secure sealing
  6. Check Anti-Loosening: Verify anti-loosening measures (e.g., threadlocker, lock washers) are properly applied
  7. Conductivity/Insulation Test: Perform electrical testing to confirm proper connection and insulation

Important Installation Notes

Electrical Safety

No hot-plugging:

Never connect or disconnect the connector while power is applied to avoid arcing or equipment damage.

Sealing Integrity

Sealing ring protection:

Ensure O-rings are not missing, damaged or improperly installed to maintain IP rating.

Cable Management

Secure cable fixing:

Fasten cables properly to avoid stress concentration at the connector interface from pulling.

Panel Mounting

Panel seal compression:

Ensure the sealing gasket is fully compressed for panel-mounted connectors.

Note: For connectors used in high-vibration environments (e.g., industrial robots, heavy machinery), additional anti-loosening measures and periodic torque checks are recommended to maintain connection reliability.